Neighborhood Action Plan Status - Phase I

JUMP TO PHASE II REPORT --- JUMP TO PHASE III REPORT


Windom
Strategy
NRP Funds Approved
Funds Contracted
Funds
Available
to Contract
Citation
Strategy Name
NRP
Allocations
Program
Income
Total
Allocations
Contract
Number
Funds
Under
Contract
Vendor
Name
01 PUBLIC SAFETY/SERVICES
1.1.2.1Promote Block Clubs     
Total
3793
 
 
 
Windom Community Council
 
02 HOUSING
2.1.1.1Establish Housing Fund$100,000.00   $100,000.00
Total
10417
$100,000.00
$100,000.00
 
Center for Energy and Environment
 
2.1.2.1Plant Trees in Open Spaces$6,000.00   $6,000.00
Total
3665
$6,000.00
$6,000.00
 
Park Board
 
07 BUSINESS
4.1.2.2Commercial Exterior Improvement Fund$100,000.00   $100,000.00
Total
11813
$100,000.00
$100,000.00
 
Center for Energy and Environment
 
09 BUILDING COMMUNITY PART 1
5.1.2.1-2Hire Staff$34,041.00   $34,041.00
Total
18165
3793
$34,041.00
$2,500.00
$31,541.00
 
Kenny Neighborhood Association
Windom Community Council
 
10 BUILDING COMMUNITY PART II
5.2.1.1.aCommunity Facility 1$16,329.82   $16,329.82
Total
3950
$16,329.82
$16,329.82
 
Minneapolis Public Works Department
 
5.2.1.1.bCommunity Facility 2$10,000.00   $10,000.00
Total
10471
$10,000.00
$10,000.00
 
School Board
 
5.2.1.1.cCommunity Facility 3$1,475,329.00   $1,475,329.00
Total
12528
11100
17711
$1,475,329.00
$1,270,000.00
$200,000.00
$5,329.00
 
School Board
School Board
Park Board
 
ROLL-OVER FUNDS
DOLLARS ROLLED OVER TO PHASE 2$7,500.18 $80,800.00 $88,300.18
See P2 SU-10
DOLLARS ROLLED OVER TO PHASE 3  $5,000.00 $5,000.00


See P3 SU-10
TOTAL$1,749,200.00 $85,800.00 $1,835,000.00
$1,741,699.82
 
Percentage of Neighborhood's Allocation that has been Contracted100%

Windom Neighborhood Action Plan Status (SU-10 P1) run on 03/28/2024 at 3:32 AM
Neighborhood name = 65 Windom