Neighborhood Action Plan Summary - Phase I
JUMP TO PHASE II REPORT --- JUMP TO PHASE III REPORT
Lind-Bohanon |
Strategy | Pre Year One | 1998 | 1999 | 2000 | 2001 | 2002 | NRP Total | Total Housing * | Program Income | Mod #s Affecting Strategy |
|
01 HOUSING |
1.1.A.1 |
Housing Improvement Program |
$163,000.00 |
_ | _ | _ | _ | _ | $163,000.00
| $163,000.00
| $136,896.05
| |
1.1.A.2 |
Home Improvement Program |
$51,700.00 |
$200,000.00 | $100,000.00 | $89,716.00 | $2,000.00 | _ | $443,416.00
| $443,416.00
| $201.43
| 5,8,22 |
1.2.A.1 |
Demo Boarded/Vacant Homes |
_ |
_ | _ | _ | _ | _ |
|
|
| 8,19 |
1.3.A.1 |
Down Payment Assistance (Humboldt) |
$3,300.00 |
_ | _ | _ | _ | _ | $3,300.00
| $3,300.00
|
| 8 |
|
02 SOCIAL ENVIRONMENT |
2.1.A.1 |
Tree Planting/Clean Public Places |
$107,000.00 |
$5,163.00 | _ | _ | _ | _ | $112,163.00
|
|
| |
2.2.A.1 |
Develop Green Places |
_ |
_ | _ | _ | _ | _ |
|
|
| 1,21 |
2.2.A.3 |
Bohanon Park Improvements |
_ |
$109,860.40 | _ | _ | _ | _ | $109,860.40
|
|
| 1,2,7,8,11 |
2.2.B.1 |
Community Center |
_ |
_ | _ | _ | _ | _ |
|
|
| 2,8,9,10,13,14,15,16,17,18,19,21 |
2.2.B.3 |
Neighborhood Events |
$2,000.00 |
$120,985.00 | $1,000.00 | _ | _ | _ | $123,985.00
| $75,630.85
|
| 12,13,14,15,16,17,18,19 |
2.2.C.2 |
Clean-Up Campaigns |
_ |
$500.00 | $877.44 | $500.00 | $500.00 | $500.00 | $2,877.44
|
|
| 8 |
2.3.A.1 |
Welcome Signs |
_ |
$2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $10,000.00
|
|
| |
2.3.A.2 |
Welcome Packets |
_ |
$390.35 | $500.00 | $500.00 | $500.00 | _ | $1,890.35
| $1,153.11
|
| 24 |
2.3.B.1 |
Neighborhood Newsletter |
_ |
$45,609.65 | $6,000.00 | $5,000.00 | $4,000.00 | $4,000.00 | $64,609.65
| $39,411.89
|
| 12,13,24 |
2.3.B.2 |
Advertise Community Events |
$3,630.68 |
$769.32 | $500.00 | $500.00 | $500.00 | $500.00 | $6,400.00
|
| $20,778.38
| 12,22 |
|
03 CRIME AND SAFETY |
3.1.A.1 |
Stroll/Bike Patrol |
_ |
$5,000.00 | $1,000.00 | _ | _ | $2,000.00 | $8,000.00
|
|
| 5,20 |
3.1.A.2 |
Organize Block Clubs |
_ |
$3,000.00 | $3,500.00 | _ | $1,500.00 | $1,500.00 | $9,500.00
|
|
| 5,20 |
3.1.D.1 |
Restorative Justice Program |
_ |
_ | _ | _ | _ | _ |
|
|
| 20 |
3.1.E.1 |
Traffic Study/Implementation |
_ |
_ | _ | _ | _ | _ |
|
|
| 20,21 |
|
04 BUSINESS |
4.1.A.1 |
Camden Physicians Clinic |
$42,731.48 |
_ | _ | _ | _ | _ | $42,731.48
|
|
| 11,12 |
4.1.A.3 |
Enterprise Facilitation |
_ |
$5,000.00 | _ | _ | _ | _ | $5,000.00
|
|
| 3,6,12,19 |
4.1.A.4 |
Commercial Improvement Fund |
_ |
$60,000.00 | _ | _ | _ | _ | $60,000.00
|
|
| 4,21 |
4.2.A.2 |
Business Corridor Acquisitions |
_ |
_ | _ | _ | _ | _ |
|
|
| 3 |
4.2.B.1 |
Lyndale Corridor Streetscape |
_ |
_ | $24,000.00 | _ | _ | _ | $24,000.00
|
| $4,221.62
| 4,21,22 |
|
05 PLAN IMPLEMENTATION |
5.1.A.1 |
First Step Implementation |
$10,000.00 |
_ | _ | _ | _ | _ | $10,000.00
| $6,100.00
|
| |
5.2.A.1 |
Action Plan Implementation Support |
$6,637.84 |
$184,662.16 | $15,400.00 | $13,400.00 | $11,400.00 | $9,400.00 | $240,900.00
| $146,949.00
|
| 6,9,10,11,13 |
|
PHASE 1r TOTAL | $15,000.00
| $64,745.68
| $147,000.00
| $500.00
|
|
| $227,245.68
|
|
| |
|
TOTAL | $405,000.00
| $807,685.56
| $301,777.44
| $112,116.00
| $22,400.00
| $19,900.00
| $1,668,879.00
| $878,960.85
| $162,097.48
| |
% FOR HOUSING | | | | | | | 61% | | |
*Some values in the Total Housing column are administrative costs that are housing related.
PLAN MODIFICATIONS |
No. | Plan Step Modified | Approved | Description |
1 | Full Action Plan | 11/17/98 | The NRP Director approved a modification to the plan to shift $13,500 in 1998 from Develop Green Spaces (Social Environment 2.A.1.) to Improve Bohanon Park (Social Environment 2.A.3.). |
2 | Full Action Plan | 07/31/00 | The NRP Director approved a modification to the plan to reallocate $115,000 in 1998 from Community Center (Social Environment 2.B.1.) to Improve Bohanon Park (Social Environment 2.A.3.). The modification also revises the wording of Home Improvement Program (Housing 1.A.2.) to include support of "Life-Cycle housing choices" to allow funding for the Humboldt Greenway Senior Housing Project. |
3 | Full Action Plan | 08/28/00 | The NRP Director approved a modification to the plan to reallocate $60,000 in 1998 from Business Corridor Acquisitions (Business 2.A.2.) to Enterprise Facilitation (Business 1.A.3.). |
4 | Full Action Plan | 03/05/01 | The NRP Director approved a modification to the plan to reallocate $30,000 in 1998 from Lyndale Corridor Streetscape (Business 2.B.1.) to Commercial Improvement Fund (Business 1.A.4.).
|
5 | Full Action Plan | 07/30/01 | The NRP Director approved a modification to the plan to reallocate $6,000 ($4,000 in 2000 and $2,000 in 2001) to Home Improvement Program (Housing 1.A.2.) from two strategies: (1) $4,500 ($2,500
in 2000 and $2,000 in 2001) from Stroll/Bike Patrol (Crime and Safety 1.A.1.); and (2) $1,500 in 2000 from Organize Block Clubs (Crime and Safety 1.A.2.).
|
6 | Full Action Plan | 10/30/01 | The NRP Director approved a modification to the plan to reallocate $25,000 in 1998 from Enterprise Facilitation (Business 1.A.3.) to Action Plan Implementation Support Plan Implementation 2.A.1.).
|
7 | Full Action Plan | 04/16/02 | The NRP Director approved, based on Policy Board and City Council approvals, a modification to the plan by revising the language of Improve Bohanon Park (Social Environment 2.A.3.) to include
improvements to the adjacent school facility.
|
8 | Full Action Plan | 03/29/04 | The NRP Director approved a modification to the plan to reallocate a total of $52,077.44 from the following strategies: (1) $20,000 in 1995/96 from Demo Boarded/Vacant Homes (Housing 2.A.);
(2) $31,700 in 1995/96 from Down Payment/Closing Cost Assistance (Housing 3.A.1.); and (3) $377.44 in 1998 from Improve Bohanon Park (Social Environment 2.A.3.). The funds are reallocated to the following
strategies: (1) $51,700 in 1995/96 to Home Improvement Program (Housing 1.A.2.); and (2) $377.44 in 1998 to Clean-Up Campaign (Social Environment 2.C.2.). The modification also revises the wording of Community
Center (Social Environment 2.B.1.) to include improvements to other public facilities.
|
9 | Full Action Plan | 07/12/04 | The NRP Director approved a modification to the plan to reallocate $24,000 in 1998 from Community Center (Social Environment 2.B.1.) to Action Plan Implementation Support (Plan
Implementation 2.A.1.). The modification also revises the language of Community Center (Social Environment 2.B.1.) to reserve $24,500 for improvements to Webber Library.
|
10 | Full Action Plan | 03/29/05 | The NRP Director approved a modification to the plan to reallocate $24,000 in 1998 from Community Center (Social Environment 2.B.1.) to Action Plan Implementation Support (Plan
Implementation 2.A.1.).
|
11 | Full Action Plan | 09/29/06 | The NRP Director approved a modification to the plan to reallocate $24,900 ($6,637.84 in 1995/96 and $18,262.16 in 1998) to Action Plan Implementation Support (Plan Implementation 2.A.1.)
from the following strategies: (1) $18,262.16 in 1998 from Improve Bohanon Park (Social Environment 2.A.3.); and (2) $6,637.84 in 1995/96 from Camden Clinic (Business 1.A.1.).
|
12 | Full Action Plan | 10/10/06 | The NRP Director approved a modification to the plan to reallocate a total of $24,900 to the following strategies: (1) $2,000 in 1995/96 to Neighborhood Events (Social Environment 2.B.3.); (2) $19,000 in 1998
to Neighborhood Newsletter (Social Environment 3.B.1.); and (3) $3,900 ($3,630.68 in 1995/96 and $269.32 in 1998) to Advertise Community Events (Social Environment 3.B.2.). The funds are reallocated from the following strategies:
(1) $5,630.68 in 1995/96 from Camden Clinic (Business 1.A.1.); and (2) $19,269.32 in 1998 from Enterprise Facilitation (Business 1.A.3.).
|
13 | Full Action Plan | 06/18/07 | The NRP Director approved a modification to the plan to reallocate $105,000 in 1998 from Community Center (Social Environment 2.B.1.) to the following strategies: (1) $10,000 in 1998 to Neighborhood
Events (Social Environment 2.B.3.); (2) $20,000 in 1998 to Neighborhood Newsletter (Social Environment 3.B.1.); and (3) $75,000 in 1998 to Action Plan Implementation Support (Plan Implementation 2.A.1.). The modification
also revises the wording of Neighborhood Events (Social Environment 2.B.3.) to include broader outreach activities.
|
14 | Full Action Plan | 03/11/08 | The NRP Director approved a modification to the plan to reallocate $12,500 in 1998 from Community Center (Social Environment 2.B.1.) to Neighborhood Events (Social Environment 2.B.3.).
|
15 | Full Action Plan | 03/31/08 | The NRP Director approved a modification to the plan to reallocate $24,995 in 1998 from Community Center (Social Environment 2.B.1.) to Neighborhood Events (Social Environment 2.B.3.) |
16 | Full Action Plan | 05/30/08 | The NRP Director approved a modification to the plan to reallocate $12,400 in 1998 from Community Center (Social Environment 2.B.1.) to Neighborhood Events (Social Environment 2.B.3.).
|
17 | Full Action Plan | 10/22/08 | The NRP Director approved a modification to the plan to reallocate $10,000 in 1998 from Community Center (Social Environment 2.B.1.) to Neighborhood Events (Social Environment 2.B.3.). |
18 | Full Action Plan | 02/23/09 | The NRP Director approved a modification to the plan to reallocate $24,990 in 1998 from Community Center (Social Environment 2.B.1.) to Neighborhood Events (Social Environment 2.B.3.).
|
19 | Full Action Plan | 04/27/09 | The NRP Director approved a modification to the plan to reallocate a total of $30,730.68 ($15,000 in 1995/96 and $15,730.68 in 1998) to a new Phase II strategy, Phase II Plan Development (Phase II
Rollover). The funds are reallocated from the following strategies: (1) $15,000 in 1995/96 from Demo Boarded/Vacant Homes (Housing 2.A.); and (2) $15,730.68 in 1998 from Enterprise Facilitiation (Business 1.A.3.). (This
is Phase I Plan Modification #19 and Phase II Plan Modification #1.) The modification also reallocates $25,100 in 1998 from Community Center (Social Environment 2.B.1.) to Neighborhood Events (Social Environment 2.B.3.).
|
20 | Full Action Plan | 06/12/09 | The NRP Director approved a modification to the plan to reallocate a total of $4,000 from the following strategies: (1) $2,000 in 1999 from Stroll/Bike Patrol (Crime and Safety 1.A.1.); and (2) $2,000 in 1998
from Restorative Justice Program (Crime and Safety 1.D.1). The funds are reallocated to the following strategies: (1) $2,000 in 1999 to Organize Block Clubs (Crime and Safety 1.A.2.); and (2) $2,000 in 1998 to Traffic Study/
Implementation (Crime and Safety 1.E.1.).
|
21 | Full Action Plan | 10/02/10 | Approval of the Phase II Action Plan reallocated a total of $196,515 from Phase I to Phase II strategies. The funds are reallocated from the following Phase I strategies: (1) $20,000 in 1998 from Develop Green Spaces (Social Environment 2.A.1.); (2) $22,015 in 1998 from Community Center (Social Environment 2.B.1.); (3) $3,500 ($2,000 in 1998; $1,000 in 1999; and $500 in 2000) from Traffic Study/Implementation (Crime and Safety 1.E.1.); (4) $5,000 in 1998 from Commercial Improvement Fund (Business 1.A.4.); and (5) $146,000 in 1999 from Lyndale Corridor Streetscape (Business 2.B.1.). The funds are reallocated to the following Phase II strategies: (1) $22,015 in 1998 to Upgrade Park Facilities (Phase II Rollover, Social and Natural Environment 1.4.2.); (2) $20,000 in 1998 to Pollution Reduction Projects (Phase II Rollover, Social and Natural Environment 2.1.1.); and (3) $154,500 ($7,000 in 1998; $147,000 in 1999; and $500 in 2000) to North Lyndale Revitalization (Phase II Rollover, Business and North Lyndale Avenue 1.1.1.). (This is Phase I Plan Modification #21 and Phase II Plan Modification #2.) |
22 | Full Action Plan | 04/20/11 | The NRP Director approved a modification to the plan to reallocate $25,000 in Program Income from Home Improvement Program (Housing 1.A.2.). The funds are reallocated to the following strategies: (1) $20,778.38 in Program Income to Advertise Community Events (Social Environment 3.B.2.); and (2) $4,221.62 in Program Income to Lyndale Corridor Streetscape (Business 2.B.1.). |
23 | Full Action Plan | 01/28/14 | The NCR Director approved a plan modification to reallocate $20,000 previously rolled over from Phase I from Pollution Reduction Projects (Social and Natural Environment 2.1.1.) to Expand Senior Activities (Social and Natural Environment 1.3.2.). (This is Phase I Plan Modification #23 and Phase II Plan Modification #3.) |
24 | Full Action Plan | 06/21/23 | The NCR Director approved an administrative modification to the plan to reallocate $609.65 in 1998 from Welcome Packets (Social Environment 3.A.2.) to Neighborhood Newsletter (Social Environment 3.B.1.).
|
|